25 July 2018
Power of Siberia Gas Pipeline Completed by 90.5 Per Cent, 1,954 Kilometers Built
Construction of a two-string crossing under the Amur River within the Power of Siberia gas pipeline is also in progress. Pipe pulling in the first tunnel was completed in July 2018.
16 July 2018
From January 1 to July 15, 2018, Gazprom’s Exports to the Far Abroad Countries amounted to 108,9 bcm
It is by 6 bcm more than in the same period of 2017
13 July 2018
Alexey Miller and Serbian Ambassador Slavenko Terzic note reliability of Russian gas supplies to Serbia
According to preliminary data, in the period from January 1 through July 12, 2018, gas exports to Serbia totaled 1.2 bcm, which is 5.3 per cent more than in the same period of 2017
6 July 2018
Gazprom and Uzbekneftegaz Discussed Ongoing Development of Shakhpakhty Field
The parties also considered the issues related to the purchases of Uzbek gas by Gazprom.
4 July 2018
Gazprom and PetroVietnam discuss progress of joint projects
Particularly, Alexey Miller and Tran Sy Thanh considered the joint project of construction of a small-scale LNG production complex
2 July 2018
Gazprom’s Exports to the Far Abroad Countries in H1 2018 Amounted to 101.2 Bcm.
It is by 5.8% (5.5 bcm) more than in the same period of 2017.